Owner
City of San Antonio

Engineer
CEC

Project Cost
$1.5 Million


public construction

Prue Road Low Water Crossing

Public Construction - Prue Road Low Water Crossing San Antonio
 

Prue Road Low Water Crossing consisted of the installation of an 8 Barrel 9’x6’ MBC structure at Huebner Creek to eliminate the low water crossing for a 100 year storm event and for a future 5-lane road section. On this project, Yantis Company proposed the idea of keeping the street completely closed during construction and pre-casting the box culvert crossing in lieu of a cast-in-place structure that allowed the roadway section to be completed and open to traffic 6 months ahead of the original project schedule as well as provided a significant overall savings to the City.